NBCC (India) has achieved a total business value of 981.17 crore in March 2022. The state-owned company on Monday announced its business performance for March.
Overall, providing comprehensive, Design, Engineering and Project Management Consultancy (PMC) services for various works in the Union Territory of Ladakh 500 crores, have already been deposited on March 17 this year.
Other than this 500 crore work order in the union territory of Ladakh, NBCC Received the following deals in March 2022.
1. Creation of border on defense land for 10 locations in Maharashtra, Punjab, Uttar Pradesh, Haryana and Karnataka. This work order is awarded by the Directorate General of Defense Defense (DGDE) whose value is 52.73 crores.
2. Additional Approval – Construction of Academic Building for Faculty of Technology (G+7 with 2 Basements) in North Campus. This work order has been given by the University of Delhi, the amount of which 21.16 crores.
3. Additional Acceptance University Interdisciplinary Creation of Academics Administrative and
Anusandhan Bhawan (G+7 with two basements) Phase-I for the prestigious Institute at Maurice Nagar. This work order is of Delhi University Aggregating 20.65 crores.
4. Additional approval for construction of hostel at Dhaka campus for reputed institute (G+9) with two basements Phase-I. The work order is received from the University of Delhi and overall 211.70 crores.
5. Construction of Interdisciplinary Academic, Administrative and Research Building for Institution of Eminence at Maurice Nagar (G+7 with two basements) Phase-II. The work order was obtained from the University of Delhi and was evaluated by 164.65 crores.
6. To provide facility management services and operation and maintenance of the Corporate Office of MSTC Limited, New Town, Kolkata. work order amount 10.28 crores.
Cumulatively, the sum of the above six orders is 481.17 crore in March 2022.
NBCC shares ended on 39.60 each lost 1.98 per cent on the BSE today.